Resource levelling

Loading...
Thumbnail Image

Keywords

Degree Level

masters

Advisor

Degree Name

M. Eng.

Volume

Issue

Publisher

Memorial University of Newfoundland

Abstract

For projects where highly skilled workers are needed whose training could take a long time, gradualness in the resource profile could provide the necessary training period. This thesis presents an heuristic procedure for optimal resource levelling achieving a gradual (parabolic) resource distribution. It aims at minimizing the fluctuation of day-to-day resource change using the variance of resource change as the primary index. Mathematically based, this heuristic gives a measure whereby an optimal schedule can be recognized. -- Using the computation procedure for this heuristic a computer programme called BACS (Build-up Activity Chain Scheduler) has been developed which yields an optimal schedule for large projects from data obtained from CPM analysis. This programme is both easy to use and has a short computational time.